Following the message issued on May 1, the project team has more detail about the new temporary traffic pattern near the Helen Hadley Hall site. Initially, the plan did not...
Upper Science Hill Development phase one construction, photo courtesy of Yale Facilities
June 2, 2025
This summer, Yale Facilities proceeds with several renovation and construction projects to enhance campus. These efforts will make the university more functional and...
Logistics plan for berm removal at the northeast corner of upper Science Hill
May 22, 2025
The Upper Science Hill Development (USHD) continues to make progress on the overall project and is reaching another milestone, razing the Pierson-Sage Parking Garage. Since...
Photo of firefighters, photo by Adobe Stock
May 6, 2025
As part of Safety Week (May 5–9), the New Haven Fire Department (NHFD) will perform mock rescue drills at Osborn Memorial Laboratories on Thursday, May 8. A live training...
Helen Hadley Hall, aerial view, Google Earth
May 1, 2025
Enabling work at Helen Hadley Hall is underway. After thoughtful analysis and consideration, Yale decided to demolish the building at 420 Temple Street. The future...
Osborne Memorial Laboratories, Kroon Hall plaza view, rendering by HGA Architects, courtesy of Yale Facilities
March 7, 2025
Enabling work at Osborn Memorial Laboratories (OML) began in earlier in 2025, marking the start of a comprehensive renovation. The project includes two new high-performance...
Logistics plan for berm removal at the northeast corner of upper Science Hill
December 4, 2024
Learn more about the work needed prior to the garage removal that will take place in December 2024. The berm surrounding the garage along Edwards Street and Whitney Avenue...